Quality project for concrete batching plant panels
Focused quality and documentation project for a batching plant manufacturer whose control panels drew repeated commissioning complaints.
- Delivery geography
- Türkiye
- Variants in scope
- 2 plants audited
- Program duration
- 4-month expert task
- Responsibility level
- Expert task
- Standards applied
- IEC 60204-1 · ISO 9001 audit practice
What the delivered system actually does.
A concrete batching plant is commissioned on site, often in a hurry, by people who did not build its control panel. When the panels draw repeated commissioning complaints, the cost is not in the panel — it is in the days lost on site and the reputation lost with the customer.
This was a focused quality and documentation project rather than a supply contract. GANI went through the panel design, the build practice and the documentation the commissioning engineers actually work from, and fixed what was making site work slow and error-prone.
The deliverable is that the next plant commissions faster. Better-labelled panels, drawings that match what was built, and a build practice that produces the same panel every time — which is what turns a commissioning visit from an investigation into a checklist.
A batching plant manufacturer faced recurring commissioning complaints on exported plants: wiring deviations, missing test evidence and drawings that did not match the shipped panels. Their dealers were absorbing rework costs and escalating.
STARTING CONDITIONPanels were built in-house from partially updated drawings, with a visual check but no structured test or as-built documentation step.
- Complaint records from dealers and site commissioning
- Current drawing set and panel BOMs
- Access to the panel shop and its build practice
- Export markets and applicable standards list
- Root-cause review of the complaint history
- Gap assessment of the panel shop against IEC 61439 practice
- Defined test and inspection plan with record templates
- As-built documentation loop closing drawings against shipped panels
- Training of the panel shop team and handover of the procedure
What the program delivers.
- Test and documentation procedure adopted as the shop standard
- Every shipped panel now accompanied by a signed test record
- Commissioning complaint stream cut off in the following quarters
- Follow-up audit agreed at twelve months