Capacity extension for a telecom access device
Parallel low-volume production of a network access device beside the OEM’s own line, grown step by step toward full outsourcing of the variant.
- Delivery geography
- Poland
- Annual volume
- ~3,200 units/year after full transfer
- Batch size
- 250–400 per call-off
- Variants in scope
- 2 variants
- Program duration
- 12 months, pilot to full transfer
- Responsibility level
- Capacity extension
- Standards applied
- IPC-A-610 Class 2 as practice · Customer test specification
What the delivered system actually does.
A network access device is the box that terminates a subscriber connection. The OEM builds the high-volume variants efficiently on their own line; what their line is bad at is the low-volume variant that interrupts it — a few hundred units of something slightly different.
This is capacity extension rather than outsourcing. The OEM keeps their own production. GANI runs the low-volume variant in parallel, in our facility, from their material specification and their production data, so their line stays on the products it is efficient at.
It has grown step by step. Each stage — first build, then test, then supply chain — was proven before the next was handed over, and the programme is moving toward full outsourcing of that variant. Nothing was transferred on trust; each step was transferred on evidence.
A telecom OEM’s main plant was saturated by a flagship product, starving a lower-volume access device of line time and pushing out lead times. They wanted a second source that mirrors their process — same test coverage, same traceability — without disturbing the running line.
STARTING CONDITIONThe device was in stable series production at the OEM, with released documentation, test software and an existing fixture design.
- Released production documentation and test software
- Reference units and the existing fixture design
- Process audit criteria from the OEM quality team
- Monthly demand split between the two sites
- Replication of the assembly and test process at GANI
- Duplicate test fixture build validated against reference units
- Pilot lots run in parallel with the OEM line for comparison
- Ramp of monthly volume as pilot criteria were met
- Shared traceability reporting into the OEM quality system
What the program delivers.
- Parallel production released after joint pilot-lot review
- Variant transferred to full outsourcing within the first year
- OEM line time freed for the flagship product
- Identical test coverage and records maintained across both sites